|
|
![]() |
| Home
> research >
corporate governance > projects >
project 28 |
|
|
|
Research Programmes Enterprise and Innovation Research Activities Survey
& Database Unit Policy Evaluation Unit SME Surveys
Other CBR Surveys |
Project:
'Capright': Resources, Rights and Capabilities in Europe
Project leader: Simon
Deakin
Overview
| Output
Update on progress: November 2010 Aims and Objectives This project is funded by the Sixth Research and Development Programme of the EU and coordinated by the IDHE-Cachan unit, based near Paris. The main contribution of the CBR has been to undertake a series of case studies of employee information and consultation mechanisms in the context of corporate restructuring. The members of the CBR team have also carried out work on the impact of transnational economic integration on the operation of labour standards at national and sectoral level, including an analysis of the law and practice relating to local labour clauses, and have worked on developing the theoretical framework for the project, which is draws on capability theory. The empirical parts of the project were completed in 2010 and the project concludes in 2011. Results A major initial focus on the research was on the lessons to be drawn from the construction of the new Terminal 5 building at Heathrow airport. The work built on a theoretical framework which stresses 'internalist' approaches to learning and governance based on the importance of communicative processes, dialogue and deliberation. Material drawn from an in-depth case study on the construction T5 was deployed to examine the development and impact of learning both within and between the subsystems of corporate governance, utilities regulation, multi-firm contracting and industrial relations in large construction projects. T5 took around 20 years to plan and build and started operations in March 2008, six years after construction started. Its opening was marked by confusion and controversy, but as a construction project, however, T5 was highly successful. It was based on a novel approach to risk-sharing between client and suppliers and it incorporated innovative mechanisms for dialogue and monitoring between the actors involved, that is, the client, BAA, the contractors on the construction and engineering sides of the project, and trade unions representing the groups of workers involved. There is evidence that these arrangements contributed positively to a number of successful project outcomes, above all the completion of the construction work on time and on budget, an above-industry health and safety record, and virtually no time lost to disputes. The case of Terminal 5 demonstrates how attempts to build a 'systemic' approach to the project revolved around the interactions between a wide range of actors and processes and beyond the contractual arrangements. However, case shows that in the absence of mechanisms of structural coupling between different subsystems, the capacity for adaptation along the lines of a dynamic learning model is reduced. Although the difficulties surrounding the opening of T5 in March 2008 were unconnected to the construction of the new Terminal, the wider future of the institutional mechanism used to promote cooperation and risk-sharing in the construction project is in doubt, in part because the model it embodies was not taken up for the 2012 London Olympics. |
|
|
|
| © 2004 Centre for Business
Research, University of Cambridge |
|